Skip to content Skip to navigation

Schedule

Expected 2018 Stanford General Use Permit Approval Process

  1. Community Open Houses Stanford receives input from the community - June 2016
  2. Apply Stanford submits application to County - November 2016
  3. Community Feedback Stanford holds Community Forum to share application details and hear from the community - January 2017
  4. Community Feedback Community provides input on what the Environmental Impact Report should study - February 2017
  5. Draft County Report County publishes Draft Environmental Impact Report - October 2017
  6. Community Feedback Community provides comments on Draft Environmental Impact Report - October 2017 to February 2018
  7. Recirculated County Report County issues recirculated portion of Draft Environmental Impact Report - June 2018
  8. Community Feedback Community provides comments on recirculated Draft Environmental Impact Report - June to July 2018
  9. County Reports Complete County issues Final Environmental Impact Report - December 2018 to April 2019
  10. Public Hearings Planning Commission workshop, hearings, and recommendations - May to June 2019
  11. Public Hearings (YOU ARE HERE) Board of Supervisors workshop, hearings, and decision - September to November 2019
  12. New General Use Permit

Tell the County you support Stanford’s plan

Show your support